GW2IE Meeting 39 -- Tues 09 June 2015

Agenda

  • Meetings update
    • OGC June TC: report (Bruce)
    • OGC Sept / HDWG: GWML2 session (Wed 23 Sept?) (Sylvain)
  • Server update
    • server availability: (Jessica)
    • domain configuration: (Bruce)
  • AquiferTest update
    • almost done: diagrams to be added (Eric)
  • Instances
    • Schema update (Francois)
    • List of instances (Boyan)
    • Instances update (All)
  • Report
    • Conceptual model update (Boyan)
    • Instance fragments update (Eric)
    • Implementation (All)
      • Review general template for use-case implementation
      • Review Use-case 5 template (for schema mappings): Summary, Methods, Similarities/Contrasts
  • Use-case roundtable
    • Aim: to complete implementation and reporting by next meeting

Participants

Results

  • Meetings update
    • OGC June TC:
      • presented with no major concerns from audience
    • OGC Sept / HDWG:
      • GWML2 session tentatively on Wed 23 Sept
      • Transport: subway/ train or possibly BRGM shuttle from Charles De Gaulle airport
      • Accommodation: BRGM investigating workshop rates, blocked rooms, shuttle transport to BRGM
  • Server update: on-track
  • AquiferTest update: in progress
  • Instances
    • Schema update:
      • Validation issues: to be resolved (Francois)
      • Missing defs: Conceptual Model EA to be sent to Francois (done)
    • List of instances:
      • unnecessary: list already complete = the list of requirements classes in report
    • Instances update
      • examples: replace outdated examples on wiki with SVN URL to most recent examples (done)
  • Report
    • Conceptual model update (Boyan)
    • Instance fragments update (Eric, Bruce)
    • Implementation documentation template:
      • deferred until implementations completed
  • Use-case roundtable: on-track
  • Future meetings
  • Timeline
    • end-June: complete instance updates in SVN
    • mid-July: complete report (including instance fragments, model updates), except use-cases
    • end July: complete use-case implementations
    • mid-Aug: complete use-case documentation and report
    • end-Aug: complete review and revision of report
    • Sept 1: submit report to HDWG for acceptance at OGC Sept TC
    • Sept 1: begin process to initiate SWG at OGC Sept TC

Connection Instructions

Ottawa Madison London Paris MelbourneSorted ascending Auckland
8:00 7:00 13:00 14:00 22:00 23:59

  • Teleconference:
    • Dial local number (see below) and passcode = 616269

Country Conference Number
Australia +61 (0) 3 8672 0180
Austria +43 (0) 1 2650500
Belgium +32 (0) 3 294 11 60
Canada +1 559-546-1300
France +33 (0) 1 80 14 11 00
Germany +49 (0) 228 5343020
Italy +39 055 464 0570
Netherlands +31 (0) 20 322 3000
Poland +48 22 116 80 20
United Kingdom +44 (0) 330 606 0182
United States +1 760-569-7100
Topic revision: r4 - 09 Jun 2015, BoyanBrodaric
This site is powered by FoswikiThe information you supply is used for OGC purposes only. We will never pass your contact details to any third party without your prior consent.
If you enter content here you are agreeing to the OGC privacy policy.

Copyright &© by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding OGC Public Wiki? Send feedback